Search This Blog

Thursday, 19 September 2013

Inter Project Transfer V/E/P



INTER PROJECT TRANSFER OF VEH/EQPT/PLANTS

          Of late it is noticed that the veh/eqpt /plants were earmarking to transfer to other projects are lying on the edge of downgradation to cl CEE /DEE or unserviceable and the same not been maintained properly. As the result the receiving project incorporated with excessive effort and unexpected time to put them on road at a new location besides incurring huge expenditure in account of spares. To overcome this problem the following points to be ensured by both projects. 

1.       The Veh /Eqpt /plants which are ear marked for transfer will be in serviceable condition without any major deficiency.

2.           At least 50% residual life required for transfer, in case all the same category veh/eqpt/plants held are over 50% stipulated life range, then the lower usage will be transferred.

3.           The BA/EM No wise details of the earmarked veh/ eqpt/plants proposed to be transferred will be intimated to HQ DGBR.

4.       Handing /conveyance contract if any, will be finalized/ concluded well in advance by the taking over project, for which required assistance will b done by the handing over project.

5.       The veh/eqpt/plants which are ordered for transfer will be collected within two months without any delay.   

6.       After transfer order no cannibalisation should be carried out from veh/eqpt/plants.

7.       PMS and handling conveyance contract wherever required will be asked by the taking over project well in advance from HQ DGBR.

8.       A team will be detailed by the handing over project, which will associated the team handing over project and will learn about operation and maintenance. The team will fully conversant with operation and maintenance instruction of the veh/eqpt/plant before moving.  

9.       The handing over project will ensure that the veh/eqpt/plant to be transferred is in fully working condition. The taking over project will ensure it is in operational and there are no major deficiencies.

10.     The transfer inspection will be carried out by the dependent work shop in front of both project’s team and the actual states of the veh/eqpt/plant should be reflected in IAF EME(E) 03/23 forms.

11.     All technical literature and tools will be issued along with veh/eqpt/plants.

12.     In case of plant, and dismantling is involved, the handover project will provide man power and their work shop will give technical guidance and assistance for dismantling the plant.

13.     If any dispute, it will be resolved in an appropriate manner. Any issue which cannot be resolved at the project level will be intimated to HQ DGBR as early as possible. Transfer should not be pending for want of any reasons.

14.     After take over the eqpt/plants, it is the responsibility of take over project that it should be functional within one month time.

15.     Fortnight progress of transfer should be intimated by the effected projects on 1st and 16th of every month to HQ DGBR TP (Res). The after complete collection receiving unit will forward a completion report by Nic mail to HQ DGBR TP (Res) and TA (E4 Repair).

          The above instructions will be followed by all the projects in letter and spirit, so transfer are effected smoothly as early as possible and lest amount of problems, delay and expenditure on re-installation & get functional at new location,

The authority for all above is HQ DGBR Letter No. 22152/Policy/DGBR/09/TP (Res) dated 11 July 2013.

In addition to the above the following points also noted:-

16.     Issue of the tank balance (HSD). The fuel tank should be filled up to the maximum if a vehicle is transferred.  If a plant/eqpt is being transferred then the fuel tank should be made empty before moving and same should be taken on ledger charge. 

17.     Log book. After making required entries from user unit like all updates, transfer inspection from concerned field Work Shop and the transfer entries from hand over SSTC, log book may be handed over to the taken over team if possible or forwarded to the concerned take over SSTC as early as possible (within two days) for their further action, under intimation to all concerned.
                                                _______________________________

No comments:

Post a Comment