JCB JS-205 Excavator

 

MAINTENANCE:-  The proper maintenance to JCB JS-205 Excavator is not only reduce its downtime and keep it in a good workability & appearances, but also it increase the performance of the excavator as well as the stipulated life. So all operators should be give care on good maintenance to JCB JS-205 Excavator in its due time as per company’s recommendation without fail. 

RECOMMENDED OIL AND PERIODICITY OF 

JCB JS-205 EXCAVATOR 

 

Sl No

Assembly

Grade of oil

Qty

Periodicity

Remarks

01

Engine Oil

SAE 15 W 40 C 14+

17.5 Ltr

250 Hrs

 

02

Hydraulic system

HLP-32 (-20 to15 o C) HLP-46 (-10 to 30oC)  HLP- 68  (0 to 40 oC)

270 Ltr

(Tank 135 Ltr)

2000 Hrs

replace Filter at !000 Hrs

03

Track Gear Box (Each side)

SGS90W/ SAE 90

5 x2 Ltr

1000 Hrs

First 250.

 

04

Swing Gear Box

SGS90W/ SAE 90

4.8 Ltr

1000 Hrs

 

05

Track Roller / Idler rollers

SGS90W/ SAE 90

 3/2 Ltr Each 

4000-4500 Hrs

 

06

Engine Coolant

ethylene glycol antifreeze                 (50-50 mixer)

28 LTR

2000 Hrs

 

07

Fuel

HSD

253 Ltr/

 

 

 

Maintenance parts

Part No

Air filter Inner   (change at1000 Hrs)

334/Y2811

Air filter Outer  (change at 500 Hrs)

334/Y2810

Hyd Filter (Filter Hammer 5 Micron)

401/A9650

Hyd (Pilot Control) filter Pilot 10 micron (Change first at 500Hrs then every 1000Hrs)

401/A9653

Fuel Filter Primary

333/E 9730

Fuel Filter

336/E9731

Fuel filter- FWS

336/F4093

Eng Lub Filter

333/Y7453

Strainer fuel

332/Y3299

Fan belt ( Belt drive L 1138)

331/44674

Tooth Tip

333/P7952

Pin Locking

980/84767

Washer (Pin locking)

980/84768

Nut track plate (shoe 500/46)

JSA0038

Bolt track plate (shoe 500/46)

332/J2833

 

Free Checks

period

1st free check

0 to 50 Hrs or 30 days from installation.

2nd free check

225 to 250 Hrs or within 3 months from commissioning.

3rd free check

475 to 500 Hrs or within 6 months from commissioning.

4th free check

950 to 1000 Hrs or within 1 year from commissioning.

 

 

New engine performance inspections:-

‘A’ Check

to be done at the time of putting the engine into service or within 50 Hrs service. In any case ‘A’ check must be done within one month after the engine put in to service.

‘B’ Check

to be done at 250 Hrs or 3 months whichever is occur first from NEPI (New engine performance inspection)

‘C’ Check

to be done at 500 Hrs or 6 months which ever occur first.

‘D’ Check

to be done at 1000 Hrs or 12 months which ever occur first.

It is the responsibility of the owner to get these checks done as per schedules.

 Technical data/ Dimensions:-

Track over carriage overall length

3550mm

 

Width over tracks

500 mm shoe

2490 mm

600 mm shoe

2590 mm

700 mm shoe

2690 mm

850 mm shoe

2840 mm

Weight (500 mm shoe)

 

20550 Kgs.

 Know your machine

Engine model 6BT 5.9, Make: Cummins. Engine warranty 15 months from the date of dispatch from factory or 12 months from the date of commissioning or 3600 Hrs operation which ever occur first.

Fuel Pump make: Mico Ltd, Self starter and Alternator make: Lucas TVS Ltd. (24 Volt)  Battery 12 V 110 AH, Make JCB, Qty 02 Nos. 

Engine valve clearance should be carried out at 1000 Hrs/ 12 months. Intake valve clearance is 0.254 mm or 0.010 inch and exhaust valve clearance is 0.508 mm or 0.020 inch.

Engine oil pressure should be more than 1 Kg/Cm2 with in 15 second after start the engine. While starting, do not engage the starter motor more than 30 sec. Wait 2 minute between each attempt to start.

Avoid idling the engine more than 10 minutes. Long Idling period may be harmful to the engine due to combustion chamber temperature drops so low that the fuel will not burn completely. Then carbon formation may clog the injector’s spry holes and also cause valve and piston rings to stick.

Do not operate the engine if the temperature of the coolant exceeds 98oC and engine oil pressure is low than 18 PSI, so frequently check the oil and coolant temperature gauges to maintain the temperature within level.

After full load operation idle the engine 3 to 5 minutes before shut down the engine so that lubrication oil and coolant to carry heat away from the combustion chamber, bearings, shaft etc. This is especially important for turbocharged engine. 

Before doing any welding works, remove connection of battery, Amplifier device, Electronic control unit (ECU) and monitor display. If failure to disconnect, the sensitive electrical equipments could be result irrecoverable damages to those equipments.

Incorrect operation, maintenance or repair to the engine and emission control system may lead to reduce product life, loss of performance or malfunction. It is the operator’s responsibility to ensure maintenance is conducted properly in accordance with the instructions. 

Note:-

1)

If operating under arduous conditions, do an engine oil flush (use the normal recommended engine oil) every 250 hours and replace the engine oil and filter. Service times may depend on fuel used.

2)

If operating in dusty condition do these tasks more frequently.

3)

If using a breaker, crusher or pulverize, refer to the service intervals for attachments as per manual.

4)

Tighten the nut and bolts at 50 hours of first use and then every 250 hours.

5)

First 250 hours service only and then every 1000 hours. (If the tracking hour is greater than 20% machine hours then sample/replace every 500 hours.)

6)

Replace every filters & lubricants at 5000 hours.

7)

Replace every filters & lubricants at 8000 hours.

8)

Every 6 months or 1000 hours whichever comes first.

 The above information is as per manufactures literature/ recommendations.                                                                                 ______