PREMATURE DOWNGRADATION

PREMATURE DOWNGRADATION OF V/E/Ps TO CLASS DEE

 While thinking about the premature downgradation of certen V/E/Ps which not complected the twin life criteria but mechanical condition is very poor.  And we hesitate how to proceed for further action, in this concept, HQ DGBR issued a fresh policy vide their letter No 55012/DGD/Poilcy/DGBR/16/E4 Tech dated 20 March 2023. A true copy of the same is attached herewith for refence of all concerned.                                                                                                                                                           __________                                                                                                                                                              

 

 

Headquarters

 

 

Dte General Border Roads

 

 

Seema Sadak Bhawan

 

 

Ring Road, Delhi Cantt

 

 

New Delhi-10

55012/DGD/Poilcy/DGBR/16/E4 Tech                                           20 March 2023

 

 

 

HQ CE (P) (All Projects)

HQ ADGBR (NE)

HQ ADGBR (NW)

Pin 9317-----

Guwahati-900885

Sector-48C

C/o 99/56 APO

C/o 99 APO

Chandigarh-160047

 

 

C/o 56 APO

EBW, WBW, ESD, WSD

 

 

 

POLICY DIRECTIVES: PREMATURE DOWNGRADATION

OF VEH/EQPT/PLANT TO CLASS DEE


1.            Plaes refer following letters:-

(a)

MoD (BR) letter No. BRDB/02/28/BEA/2010 dated 06 Apr 2017.

(b)

MoD (BR) letter No. 04/696/2015/D&P (BR-1) dated 11 Aug 2017.

(c)

MoD (BR) F.No. 04/696/2015/D&P (BR-1) dated 03 Feb 2022.

 

2.        Pursuant to clarification issued by MoD (BR) vide their letter under reference at para 1 (c) and observation raised by PCDA (BR) vide their letter No AT/BR/118/L.S./GoI/VOL-XXVII/ dated 28 Jan 2023, there is a need to streamline proceedures for premature downgradation of V/E/Ps to class DEE. Apropos, all cases of premature downgradtion as per the policy under reference at para 1 (a) & (c) above will be regularized by respective CFAs (to be decided as per depreciated value of V/E/Ps). However effective technical control in all cases, In-Principal Approval for premature downgradation of V/E/Ps (where twin life criteria not met) are to be proposed to HQs DGBR by concerned project through their respective ADGBR HQs along with following:-

(a)

Statement of Case duly recommended by all commanders in chain i.e. OC unit, Commander TF, CE (P) & ADGBR.

(b)

Inspection Form.

(c)

Calculation Sheet.

(d)

Cost of required spares for repair.


3.     On In-principle Approval from HQs DGBR, C of I Cum TBOO to be convened by repective project HQs.

4.      Finalisation of C of I cum TBOO and regularization of loss statement will be as per para 1067 and 1068 of BR regulation read in conjunction with MoD (BR) letter at para 1 (c) above.  In all cases of premature downgradation of V/E/Ps, above Rs 25 lakh directives on C of I cum TBOO will be given by DGBR and the same will be regularized under the power of MoD (BR) as given at srl No 8 of MoD (BR) letter No F. No 04/696/2015/D&P (BR-1) dated 03 Feb 2022.

5.    After regularization of loss, the V/E/P will be downgraded to class DEE and technical confirmation will be issued by respective Dir EME/ Dy Commandant of BW and ‘Administrative approval will be issued respective CFAs. For all cases of premature downgradation, copy of such order will be submitted to all concerned officers by the project/ BW.

6.  Time-line for process of premature downgradation cases of V/E/P for order and regularization of loss to be strictly followed as per Appx attached.

7.       This is issued with the concurrence of IFA (BR) vide their I.D.No. IF/801/Vol-XVIII/Non Pro L-03/93/&04/553/P-5 dated 28 Feb 2023.

8.    This will be come into effect the date of issue of this letter and supersedes all previous policies on the subject.

 

 

 

Sd/xxx

 

 

(Alok V Mishra)

 

 

DDG (TA)

 

 

For DGBR

Copy to:-

 

 

IFA (BR)

-           For info pl.

 

PCDA (BR)

-           For info pl.                   

 

Internal:-

HQ DGBR E4 Rep


-        For info pl.

HQ DGBR /E3ES

-        For info pl.

HQ DGBR E4 Inv

-        For info pl.


Appx of HQ DGBR letter 55012/DGD/ Policy/

DGBR/16/E4 Tech dated 20 March 2023.

TIME LINE FOR SANCTION OF PREMATURE DOWNGRADATION

OF V/E/P TO CLASS DEE

Sl No

Action

Unit

Time

Remarks

1.

Initiation of cases for premature downgradation of V/E/Ps

Initiation by user/ unit to dispatch to HQ DGBR for in principle sanction through all chain in command

15 days

Preparation of documents as per directives.

2.

Grant of in-principle sanction

By HQ DGBR/E4 Tech

6 days.

 

3.

Issue of convening order

By project HQ/BW

6 days

 

4.

Preparation/completion of C of I,TBOO by Board.

By project/ BOO

60 to 75 days

 

5.

Process of cases and Accord of sanction on C of I cum TBOO and regularization of Loss Statement by respective CFAs.

By CE projects for project level/ HQ ADGBR for cases under ADGBR.

15 to 30 days

 

6.

If approval of DGBR and MoD (BR) is required

By HQ DGBR

15 days

 

Total

120 to 150 days (Approx.)

                                                                                                                                                                       

Sd/xxx

(Alok V Mishra)

DDG (TA)

For DGBR




2 comments:

  1. BP Auto Spare Parts can be your better choice for Mahindra Scorpio Pickup spare parts due to their genuine parts, comprehensive range of options, high-quality and durable parts, expertise and experience, competitive pricing, convenient online shopping, fast shipping and reliable delivery, and excellent customer service. Choosing genuine MAHINDRA SPARE PARTS from a reliable supplier like BP Auto Spare Parts can ensure that your Mahindra Scorpio Pickup continues to perform at its best, providing you with peace of mind and confidence on the road.

    ReplyDelete
  2. Amazing Content Your BlogSpot Thanks For Sharing
    Free Professional courses

    ReplyDelete